Standard Cement Consumption for the Construction Works

The standard cement consumption for the Construction works involving in the cement as one of the raw material requires cement consumption and the coefficients for various estimation of quantities and cost of  works. The Coefficients of cement consumption works for various building construction activities involving cement mortar, concrete etc.

cement consumption
cement consumption
S. No. Cement consumption Construction Work Details The Coefficient
1 The P.C.C. (1:5:10) 2.6 Bags/cu.mt.
2 The P.C.C. (1:4:8) 3.4 Bags/cu.mt.
3 The P.C.C. (1:3:6) 4.4 Bags/cu.mt.
4 The R.C.C. M-15 (1:2:4) 6.3 Bags/cu.mt.
5 The R.C.C. M-20 (1:2:4) 8.00 Bags/cu.mt.
6 The R.C.C. M-25 (1:1:2) 12.20 Bags/cu.mt.
7 The Brick work in CM (1:6) 1.32 Bags/cu.mt.
8 The Brick work in CM (1:4) 1.90 Bags/cu.mt.
9 The Half Brickwork in (1:4) 0.213 Bags/Sq.mt.
10 The Plastering in CM (1:4) – 15mm thick 0.131 Bags/Sq.mt.
11 The Plastering in CM (1:4) – 12mm thick 0.109 Bags/Sq.mt.
12 The Plastering in CM (1:4) – 6mm thick 0.055 Bags/Sq.mt.
13 The Plastering in CM (1:6) – 15mm thick 0.086 Bags/Sq.mt.
14 The Plastering in CM (1:6) – 12mm thick 0.072 Bags/Sq.mt.
15 The Plastering in CM (1:6) – 6 mm thick 0.073 Bags/Sq.mt.
16 The 20mm thick sand face plastering in two layers. (13 mm thick plaster in CM 1:4 and 7 mm thick plaster in CM 1:2) 0.220 Bags/Sq.mt.
17 The Plastering in CM (1:3) – 13mm thick 0.157 Bags/Sq.mt.
18 The Plastering in CM (1:4) – 13 mm thick 0.117 Bags/Sq.mt.
19 The Plastering in CM (1:3) – 20mm thick 0.228 Bags/Sq.mt.
20 The Plastering in CM (1:4) – 20mm thick 0.170 Bags/Sq.mt.
21 The Floating coat of neat cement 0.044 Bags/Sq.mt.
22 The Brick on edge pitching in CM (1:4) 0.138 Bags/Sq.mt.
23 The Brick on edge pitching in CM (1:3) 0.185 Bags/Sq.mt.
24 The Flush pointing in brick work with CM (1:3) 0.031 Bags/Sq.mt.
25 The 40mm thick Damp proof course in M-20 0.32 Bags/Sq.mt.
26 The 25 mm thick IPS in M-15 0.244 Bags/Sq.mt.
27 The 40 mm thick IPS in M-15 0.340 Bags/Sq.mt.
28 The 50mm thick granite flooring, 1st layer 35mm thick (1:1.5:3), 2nd layer 15 thick (1:2) 0.433 Bags/Sq.mt
29 The 125mm high plaster skirting in CM (1:3) 0.034 Bags/R.M.
30 The 25mm thick kota stone over 20mm thick bedding in CM (1:6) 0.24 Bags/Sq.mt.
31 The 40mm thick kota stone over 20 mm thick bedding in CM (1:6) 0.264 Bags/Sq.mt.
32 The 18mm thick kota stone over 12 mm thick bedding in CM (1:6) 0.264 Bags/Sq.mt.
33 The 6 mm thick glazed tiles fixing 0.088 Bags/Sq.mt.
34 The 25mm thick CM screed in CM (1:5) 0.218 Bags/Sq.mt.
35 The 20mm thick mosaic tiles over 25mm thick bedding in CM (1:6) 0.228 Bags/Sq.mt.
36 The 18mm thick mosaic tiles over 20mm thick bedding in CM (1:6) 0.200 Bags/Sq.mt.
37 The 18mm thick marble skirting over 12mm thick bedding in CM (1:6) 0.160 Bags/Sq.mt.
38 The Water Proofing treatment with 50mm thick screed in CM (1:5), 115 thick brick bats in CM (1:3), third layer of 25 mm thick in CM (1:3) 1.18 Bags/Sq.mt.
39 The Fixing of rainwater Pipes
The 110 mm diameter PVC 0.048 Bags/Opening
The 160mm diameter PVC 0.075 Bags/Opening
40 The Joining & Fixing of CI rainwater Pipes
The 100 mm diameter 0.176 Bags/100 mtr.
The 150 mm diameter 0.264 Bags/100 mtr.
41 The Fixing wooden Frame/Steel frame doors in M-15 concrete of block size. 350 x 100 x 100 mm 0.129 Bags/Door
42 The Fixing of steel louvers/windows in M-15 grade concrete of block 150 x 50 x 50 at 750 mm c/c. 0.008 Bags/Sq.mt
43 The Fixing of rolling shutters. 0.70 Bags/ 100 Sq.Mt.
44 The Providing and Fixing of 50mm thick RCC jali. 0.329 Bags/Sq.mt.
45 The Fixing of 50 mm thick RCC Jali. 0.051 Bags/Sq.mt.
46 The Fixing of glazed earthen ware Orissa pan type water closet. 0.5 Bags/No’s
47 The Fixing of white glazed EWC. 0.05 Bags/No’s
48 The Fixing of large flat back urinal. 0.03 Bags/No’s
49 The Fixing of hand wash basin/sink 0.03 Bags/No’s
50 The Fixing of floor trap of 100/100 mm 0.05 Bags/No’s
51 The Jointing and fixing of soil waste Pipe.
80mm diameter. 0.132 Bags/RM
100mm diameter. 0.176 Bags/RM
150mm diameter. 0.264 Bags/RM
52 The Fixing of GI water pipes concealed work.
15 mm diameter 0.642 Bags/100M
20 mm diameter 0.770 Bags/100M
25 mm diameter 0.90 Bags/100M
32 mm diameter 0.96 Bags/100M
53 The Construction of brick masonry valve chambers of size 300 x 300 x 600 mm CM (1:4) fixing cover in M-15 concrete, M-15 foundation concrete 13mm thick plaster on inside & outside exposed surface. 0.700 Bags/No’s
54 The Construction of brick masonry inspection chamber of size 750 x 750 x 1000 mm in CM (1:4) RCC of M-15, 13mm plastering in CM (1:3). 5.0 Bags/No’s

our other blogs https://materialthing.com/the-cement-industry-in-india-cement-factory-in-india/

our other blogs https://materialthing.com/list-of-raw-materials-in-cement-manufacturing/

for more information please visit facebook.com/materialthing

About the author

Nayan Wakikar

hello there !
my name is Nayan Deepakrao Wakikar
currently Im a student and writing is my passion
so i created this blog for the information purpose
hope you like it if found helpful please share ! thankyou !!!

cheers
Nayan!

View all posts